Off-plan property in Nigeria: the risks and the checks

What buying off-plan means, why deposits are at risk, and the contract terms, payment limits and developer checks that protect you before you pay.

Olamide AlowoojaFounder and CEO, Zedo6 min read

Off-plan property in Nigeria: the risks and the checks

Key takeaways

  • Off-plan means paying for a property before it is built, often at a lower price, with the risk of delay, change or non-delivery.
  • Reported guidance says buyer deposits are typically not held in escrow, so developers may use them as construction money.
  • Verify the developer, the land title and the permits, visit finished projects and pay through a lawyer in stages tied to progress.
  • The contract should state a completion date, delay penalties, a refund with interest and a registered deed with consent on completion.

Off-plan property is sold before it is built. The buyer sees a drawing, a model or a show flat, pays a deposit and then pays further instalments while the building goes up. The attraction is a lower price, and sometimes a payment plan that matches your income. The risk is that you are paying for something that may be late, different from the promise or never finished. This guide explains how to judge an off-plan offer and how to protect your money.

Why people buy off-plan

Price

Early buyers are often offered a lower price than the finished home.

Payment plans

Instalments can be easier than a lump sum.

Choice

You may be able to choose the unit, floor or finish before others.

Growth

Some buyers hope the value will rise by completion.

These are real attractions. They are also exactly what makes off-plan marketing persuasive, so be sure the price and the plan make sense once the risks are counted.

The main risks

Published legal commentary on off-plan purchases in Lagos and Nigeria points to several recurring problems (Mondaq, off-plan purchases in Lagos, Mondaq, what the contracts say and do not say):

  1. 1
    Deposits are usually not ring-fenced. Buyer money is typically not held in an escrow or stakeholder account, so developers can use it as construction funding, sometimes with little of their own money in the project.
  2. 2
    Recovery is hard. If a project fails, buyers often struggle to recover deposits, even through court.
  3. 3
    Delays and approvals. Missing permits can lead to stop-work orders, and the cost often falls on buyers through longer timelines.
  4. 4
    Title defects. The most dangerous trap is a developer who does not hold proper title to the land, or who sells land they do not own.
  5. 5
    A fragmented legal framework. A law-firm report describes the rules as fragmented and inadequate for the risks involved.

What is changing, and what is not yet

The federal government has been developing a national housing and built-environment regulation policy that would require developer licensing and regulated escrow for off-plan sales. Experts quoted in the press say escrow alone would not be enough, and that the framework must also track how funds are used and whether construction milestones are met (Nairametrics, The Guardian). Until rules like these are in force and tested, the protection must come from your own checks and contract.

Before you pay: check the developer

A company registration at the Corporate Affairs Commission proves only that a company exists. It does not show that the company is honest, solvent or that it owns the land. Do these things as well.

  • Visit finished projects by the same developer, and speak to residents about delivery, quality and the paperwork they received.
  • Ask for the root title to the land, and check it with your lawyer. See Certificate of Occupancy explained and how to search a land title in Lagos.
  • Ask for building permits and approvals from the relevant planning authority, and check them with the issuing office.
  • Ask how the project is funded. Is it self-funded, bank-funded or dependent on buyers' deposits?
  • Search for complaints about the developer in the press, social media and court records.
  • Read how to verify an estate developer for a fuller checklist.

Pay safely

One published guide suggests not paying more than about half before the building reaches roof level, and tying each payment to verified construction progress (Ownkey). Treat that as a starting point for your lawyer's advice, not a rule. A good payment schedule gives the developer enough to build and leaves you enough leverage.

What the contract should say

Ask your lawyer to check that the sale agreement contains:

  1. 1
    A firm completion date, with a defined grace period.
  2. 2
    Penalties for delay, such as a discount or compensation for each month of delay.
  3. 3
    A refund with interest if the developer abandons the project or misses a long-stop date.
  4. 4
    A clear description of the unit, with plans, size, finishes and fittings attached.
  5. 5
    A narrow force majeure clause, so that ordinary delays are not excused as "acts of God".
  6. 6
    The documents you will receive on completion, including a registered deed of assignment and the governor's consent. See deed of assignment explained.
  7. 7
    What happens to your payments if you cannot continue, and whether you may transfer your unit to someone else.

What you can do if the project stalls

Keep every document and message. Ask the developer for a written update with a date. If the answers stop, speak to your lawyer about a formal demand and your options. Other buyers in the same project may be in the same position, and acting together can be more effective. Do not pay further instalments while the position is unclear.

A fair test of any off-plan offer

Ask yourself three questions.

  1. If this project is a year late, can I live with it? Where will you stay and what will it cost?
  2. If I lose most of my deposit, can I afford it? Only put in what you can afford to lose.
  3. Is the saving worth the risk? Compare the discount with the price of a finished home that you can inspect today.

If you prefer certainty, look at finished homes. On Zedo you can describe the home you want and see listings from verified agents, and the move-in cost calculator helps you compare the real cost of buying and renting.

A worked example of staged payments

Suppose a flat is priced at ₦60,000,000 on a payment plan. These figures are illustrative.

Stage Payment Condition before you pay
Reservation ₦3,000,000 Title, approvals and contract reviewed by your lawyer
Signing ₦12,000,000 Signed contract with completion date and refund terms
Foundation complete ₦9,000,000 Verified by an independent engineer
Roof complete ₦12,000,000 Verified by an independent engineer
Finishing ₦12,000,000 Verified progress and a handover date
Handover ₦12,000,000 Deed, consent and registered documents ready

The point of staging is that each payment follows evidence, so the developer's cash comes from progress, not promises. A developer who refuses any staging, and wants most of the money upfront, is telling you something.

Questions to put to the developer in writing

  • What is the exact completion date, and what happens if it is missed?
  • Where is my money held between payments?
  • What approvals are in place, and what is pending?
  • What happens if the project is abandoned or the company fails?
  • Can my lawyer and an engineer inspect the site and the documents?

Keep the answers. They are useful evidence if there is a dispute.

Sources

Several of these sources are law-firm notes or marketplace blogs. Rules and proposals change, so confirm the current position with a Nigerian property lawyer.

Common questions

What does off-plan mean?

Buying a property from drawings or a plan, before or during construction, usually in instalments over the build period.

Are off-plan deposits protected in Nigeria?

Published legal commentary says deposits are typically not ring-fenced in escrow, and proposed rules requiring escrow were still at the policy stage in mid-2026. Build the protection into your own contract.

How much should I pay before the building is up?

Guides suggest limiting upfront payments and tying each release to verified progress. Ask your lawyer what is reasonable for your project.

What if the developer does not finish?

Recovery can be hard, even through court. That is why checks, staged payments and a refund clause matter before you pay.

Written and reviewed by Olamide Alowooja. This article is general information, not legal or financial advice. Last updated 24 November 2026.